Buildings and Facilities22LA0011

CONSTRUCTION OF MULTI-PURPOSE BUILDING, LAAK CENTRAL ES, BARANGAY POBLACION LAAK, DAVAO DE ORO

CONSTRUCTION OF MULTI-PURPOSE BUILDING, LAAK CENTRAL ES, BARANGAY POBLACION LAAK, DAVAO DE ORO is a DPWH-tracked public work in Davao de Oro 1st DEO, Region XI. Reported contract value: ₱4,949,958.06. Status: Reported complete (DPWH). Contractor on record: AGONG BUILDERS AND CONST SUPPLY INC. Figures trace to dpwh.

Davao de Oro 1st DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Batutu River leading to Manat River, Barangay Banag-Banag, Montevista, Davao de Oro
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-22-0005355

₱183,146.00 · FY2022

Released to Davao del Norte State College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱4,949,958.06

Progress

Reported complete (DPWH)

Start Date

March 29, 2022

Target End

July 16, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.