GAA 2016 MFO-116F00118

REHAB./RECONST. OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE: SECONDARY ROADS, ALBAY WEST COAST ROAD:K0495+560-K0495+586; K0500+335-K0500+358; K0501+337-K0501+414; K0504+041-K0504+087; K0506+734-K0506+755;K0512+471-K0512+615;K0515+394-K0515+

REHAB./RECONST. OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE: SECONDARY ROADS, ALBAY WEST COAST ROAD:K0495+560-K0495+586; K0500+335-K0500+358; K0501+337-K0501+414; K0504+041-K0504+087; K0506+734-K0506+755;K0512+471-K0512+615;K0515+394-K0515+ is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱63,413,132.76. Status: Reported complete (DPWH). Contractor on record: SUNWEST INC FORMERLY: SUNWEST CONST. Figures trace to dpwh.

Region V, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

738 projects · ₱73.0B total · 0 flags

4. Implementation

Contract Amount

₱63,413,132.76

Progress

Reported complete (DPWH)

Start Date

May 17, 2017

Target End

May 25, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.