Construction of Flood Mitigation Structure21FH0100

Construction of River Flood Control Structure (Phase 2), Barangay Mabini Proper, Caramoran, Catanduanes

Construction of River Flood Control Structure (Phase 2), Barangay Mabini Proper, Caramoran, Catanduanes is a DPWH-tracked public work in CATANDUANES, Region V. Reported contract value: ₱14,837,820.39. Status: Reported complete (DPWH). Contractor on record: MECHANICS CONST CORP. Figures trace to sumbong.

CATANDUANES, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of River Flood Control Structure (Phase 2), Barangay Mabini Proper, Caramoran, Catanduanes
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱404,461,000.00 · FY2021

Released to Cavite 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014195

₱80,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007545

₱71,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013873

₱45,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0011481

₱30,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007593

₱9,792,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013886

₱81,000,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱14.8M total · 0 flags

4. Implementation

Contract Amount

₱14,837,820.39

Progress

Reported complete (DPWH)

Start Date

August 9, 2021

Target End

April 5, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.