Flood Control and Drainage25CD0027

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PABAHAY 2000, BARANGAY MUZON, CITY OF SAN JOSE DEL MONTE, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PABAHAY 2000, BARANGAY MUZON, CITY OF SAN JOSE DEL MONTE, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱52,603,733.05. Status: Past target date (DPWH On-Going). Contractor on record: FLORDES CONST. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Pandayan-Saluysoy Creek, Barangay Saluysoy, Meycauayan City, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-25-0007502

₱7,279,122.00 · FY2025

Released to Surigao del Norte State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

333 projects · ₱17.6B total · 0 flags

4. Implementation

Contract Amount

₱52,603,733.05

Progress

Past target date (DPWH On-Going)

Start Date

February 27, 2025

Target End

August 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.