Construction of Flood Mitigation Structure22OC0191

Construction of Flood Mitigation Structure, Parañaque City

Construction of Flood Mitigation Structure, Parañaque City is a DPWH-tracked public work in CITY OF PARAÑAQUE (METROPOLITAN MANILA), PARAÑAQUE CITY, National Capital Region. Reported contract value: ₱4,950,000.00. Status: Reported complete (DPWH). Contractor on record: G F ROVERO MERCHANDISING. Figures trace to sumbong.

CITY OF PARAÑAQUE (METROPOLITAN MANILA), PARAÑAQUE CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Para±aque City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-22-0006970

₱0.00 · FY2022

Released to Regional Office - CAR (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003020

₱287,986,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0007225

₱945,393.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0009235

₱270,626.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001728

₱75,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003128

₱703,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

234 projects · ₱3.4B total · 2 flags

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Reported complete (DPWH)

Start Date

October 10, 2022

Target End

February 6, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.