Water Provision and Storage22NC0048

CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM (RWCS) AT 14 LOCATIONS OF AGUSAN DEL SUR , EBRO ELEM. SCH.., ORMACA ELEM SCH, ANTIOQUIA ELEM SCH., SINGANAN ELEM SCH., SALVACION NATIONAL HIGH SCH., MELFREDA ELEM. SCH., KAANGAYAN ELEM. SCH., MALIPAYON ELEM SCH

CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM (RWCS) AT 14 LOCATIONS OF AGUSAN DEL SUR , EBRO ELEM. SCH.., ORMACA ELEM SCH, ANTIOQUIA ELEM SCH., SINGANAN ELEM SCH., SALVACION NATIONAL HIGH SCH., MELFREDA ELEM. SCH., KAANGAYAN ELEM. SCH., MALIPAYON ELEM SCH is a DPWH-tracked public work in Agusan del Sur 2nd DEO, Region XIII. Reported contract value: ₱2,912,132.46. Status: Reported complete (DPWH). Contractor on record: MRS BUILDERS AND SUPPLY. Figures trace to dpwh.

Agusan del Sur 2nd DEO, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Agusan River Flood Control, Sta. Josefa, Agusan Del Sur
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-22-0004840

₱28,591,106.00 · FY2022

Released to Regional Office XIII (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

180 projects · ₱1.0B total · 0 flags

4. Implementation

Contract Amount

₱2,912,132.46

Progress

Reported complete (DPWH)

Start Date

October 17, 2022

Target End

February 13, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.