Buildings and Facilities21EI0139

CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT) AT PINAMALAYAN, ORIENTAL MINDORO

CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT) AT PINAMALAYAN, ORIENTAL MINDORO is a DPWH-tracked public work in Southern Mindoro DEO, Region IV-B. Reported contract value: ₱17,639,993.63. Status: Reported complete (DPWH). Contractor on record: ALBERTO UY CONST. Figures trace to dpwh.

Southern Mindoro DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱2,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Balite River, Brgy. M. Adriatico, Gloria, Oriental Mindoro
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVI-21-0002656

₱163,085,000.00 · FY2021

Released to Bacolod City District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱17,639,993.63

Progress

Reported complete (DPWH)

Start Date

April 8, 2022

Target End

January 17, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.