Bridges, Roads20L00110

ROAD UPGRADING OF NHJ BUSO - SO. PAYPAY - TAGBINONGA - SO. CALATAGAN, CALAPAGAN - SO. MATIGDAO, MARAYAG - SO. CALINAWAN, TAOCANGA ROAD, PACKAGE 2, DAVAO ORIENTAL

ROAD UPGRADING OF NHJ BUSO - SO. PAYPAY - TAGBINONGA - SO. CALATAGAN, CALAPAGAN - SO. MATIGDAO, MARAYAG - SO. CALINAWAN, TAOCANGA ROAD, PACKAGE 2, DAVAO ORIENTAL is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱172,703,783.56. Status: Past target date (DPWH On-Going). Contractor on record: THREE W BUILDERS INC. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

416 projects · ₱20.3B total · 2 flags

4. Implementation

Contract Amount

₱172,703,783.56

Progress

Past target date (DPWH On-Going)

Start Date

October 20, 2020

Target End

December 14, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.