Bridges17IB0089

RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES AT STA. CRUZ BRIDGE (B00500SM) ALONG JCT. BUENAVISTA - LAWAAN - MARABUT ROAD

RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES AT STA. CRUZ BRIDGE (B00500SM) ALONG JCT. BUENAVISTA - LAWAAN - MARABUT ROAD is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱3,758,700.27. Status: Reported complete (DPWH). Contractor on record: 888 ACY ENT. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱2,018,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control along Boblaran River (Sta. 0+245 - Sta. 0+277.2) protecting Jct. Taft-Oras-San Policarpo-Arteche Road, Arteche, Eastern Samar
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-17-0013214

₱179,017.00 · FY2017

Released to Mulapula National Rel High School to (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

292 projects · ₱9.1B total · 5 flags

4. Implementation

Contract Amount

₱3,758,700.27

Progress

Reported complete (DPWH)

Start Date

June 5, 2017

Target End

September 17, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.