Roads23D00045

CONSTRUCTION OF TALISOY - APAD ROAD, BARANGAY BUKAL - APAD SECTION, JOMALIG, QUEZON

CONSTRUCTION OF TALISOY - APAD ROAD, BARANGAY BUKAL - APAD SECTION, JOMALIG, QUEZON is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱28,949,994.65. Status: Reported complete (DPWH). Contractor on record: OIKODOMEO CONST CORP. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱28,949,994.65

Progress

Reported complete (DPWH)

Start Date

April 11, 2023

Target End

October 16, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.