Construction of Flood Mitigation Structure22IK0034

Construction of Flood Control Protection Works Structure, Sawa Bridge, Brgy. Sawa, Basey, Samar along Basey - Sohoton Road, Basey, Samar

Construction of Flood Control Protection Works Structure, Sawa Bridge, Brgy. Sawa, Basey, Samar along Basey - Sohoton Road, Basey, Samar is a DPWH-tracked public work in BASEY (SAMAR (WESTERN SAMAR)), SAMAR (WESTERN SAMAR), Region VIII. Reported contract value: ₱22,538,367.58. Status: Reported complete (DPWH). Contractor on record: JFR CONST INC FORMERLY:JFR CONST. Figures trace to sumbong.

BASEY (SAMAR (WESTERN SAMAR)), SAMAR (WESTERN SAMAR), Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱23,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Protection Works Structure, Sawa Bridge, Brgy. Sawa, Basey, Samar along Basey - Sohoton Road, Basey, Samar
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-22-0008683

₱36,632.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002731

₱788,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱22,538,367.58

Progress

Reported complete (DPWH)

Start Date

February 14, 2022

Target End

October 16, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.