Construction of Flood Mitigation Structure23KC0017

Construction of Flood Mitigation Structure along Barandias-Dominorog Rd (Upstream) of Dominorog Bridge, Talakag, Bukidnon

Construction of Flood Mitigation Structure along Barandias-Dominorog Rd (Upstream) of Dominorog Bridge, Talakag, Bukidnon is a DPWH-tracked public work in TALAKAG (BUKIDNON), BUKIDNON, Region X. Reported contract value: ₱7,448,000.00. Status: Reported complete (DPWH). Contractor on record: VEN RAY CONST CORP. Figures trace to sumbong.

TALAKAG (BUKIDNON), BUKIDNON, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱7,600,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Barandias-Dominorog Rd (Upstream) of Dominorog Bridge, Talakag, Bukidnon
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-23-0023608

₱5,000,000.00 · FY2023

Released to 0000000 Nueva Ecija - University of Science and Technology (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱7,448,000.00

Progress

Reported complete (DPWH)

Start Date

February 27, 2023

Target End

June 23, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.