Buildings and Facilities23HN0069

CSSP: BIP - MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY PULPOGAN, CONSOLACION, CEBU

CSSP: BIP - MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY PULPOGAN, CONSOLACION, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱4,946,979.05. Status: Reported complete (DPWH). Contractor on record: GRAND TAISHAN CONST AND DEVELOPMENT INC 49251. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱8,238,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cansaga River, Barangay Danglag, Consolacion, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-23-001968

₱52,690,068.00 · FY2023

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 49251

12 projects · ₱77.7M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BASAK SAN NICOLAS, CEBU CITY, CEBU

Cebu City DEO, Region VII

2023₱14.8M
Reported complete (DPWH)
No sat.

CSSP: BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT THE OLANGO MINI CITY HALL COMPOUND, OLANGO ISLAND, LAPU-LAPU CITY, CEBU

Cebu 6th DEO, Region VII

2023₱9.9M
Reported complete (DPWH)
No sat.

SSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES- CONSTRUCTION OF EVACUATION CENTER AT OLANGO ISLAND (PHASE 3), LAPU-LAPU CITY, CEBU

Cebu 6th DEO, Region VII

2025₱9.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BASAK SAN NICOLAS, CEBU CITY

Cebu City DEO, Region VII

2024₱5.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CSSP: BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. PAJO, CITY OF LAPU-LAPU, CEBU

Cebu 6th DEO, Region VII

2023₱5.0M
Reported complete (DPWH)
No sat.

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT THE OLANGO MINI CITY HALL COMPOUND (PHASE 2), OLANGO ISLAND, LAPU-LAPU CITY, CEBU

Cebu 6th DEO, Region VII

2024₱4.9M
Reported complete (DPWH)
View all 12 projects →

4. Implementation

Contract Amount

₱4,946,979.05

Progress

Reported complete (DPWH)

Start Date

April 5, 2023

Target End

September 30, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.