Buildings and Facilities24HN0145

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT THE OLANGO MINI CITY HALL COMPOUND (PHASE 2), OLANGO ISLAND, LAPU-LAPU CITY, CEBU

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT THE OLANGO MINI CITY HALL COMPOUND (PHASE 2), OLANGO ISLAND, LAPU-LAPU CITY, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱4,945,060.66. Status: Reported complete (DPWH). Contractor on record: GRAND TAISHAN CONST AND DEVELOPMENT INC. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Gate at Basak Creek, Lapu - Lapu City, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Cebu 6th DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

12 projects · ₱77.7M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BASAK SAN NICOLAS, CEBU CITY, CEBU

Cebu City DEO, Region VII

2023₱14.8M
Reported complete (DPWH)
No sat.

CSSP: BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT THE OLANGO MINI CITY HALL COMPOUND, OLANGO ISLAND, LAPU-LAPU CITY, CEBU

Cebu 6th DEO, Region VII

2023₱9.9M
Reported complete (DPWH)
No sat.

SSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES- CONSTRUCTION OF EVACUATION CENTER AT OLANGO ISLAND (PHASE 3), LAPU-LAPU CITY, CEBU

Cebu 6th DEO, Region VII

2025₱9.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BASAK SAN NICOLAS, CEBU CITY

Cebu City DEO, Region VII

2024₱5.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CSSP: BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. PAJO, CITY OF LAPU-LAPU, CEBU

Cebu 6th DEO, Region VII

2023₱5.0M
Reported complete (DPWH)
No sat.

CSSP: BIP - MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY PULPOGAN, CONSOLACION, CEBU

Cebu 6th DEO, Region VII

2023₱4.9M
Reported complete (DPWH)
View all 12 projects →

4. Implementation

Contract Amount

₱4,945,060.66

Progress

Reported complete (DPWH)

Start Date

May 2, 2024

Target End

December 4, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.