Roads24J00094

CONSTRUCTION /UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS SECONDARY ROADS - SEIT TAYUNGAN - CAMP ANDRES ROAD - (SOOO20SL)

CONSTRUCTION /UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS SECONDARY ROADS - SEIT TAYUNGAN - CAMP ANDRES ROAD - (SOOO20SL) is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱69,475,771.68. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ZHEREB CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱69,475,771.68

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 13, 2024

Target End

March 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.