Roads24IG0045

CONSTRUCTION OF ROAD LEADING TO KAWASAN FALLS, BRGY. BINULHO, JAVIER, LEYTE

CONSTRUCTION OF ROAD LEADING TO KAWASAN FALLS, BRGY. BINULHO, JAVIER, LEYTE is a DPWH-tracked public work in Leyte 5th DEO, Region VIII. Reported contract value: ₱23,822,954.12. Status: Reported complete (DPWH). Contractor on record: WP ALVERO CONST SERVICES. Figures trace to dpwh.

Leyte 5th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Ugayon Flood Control Structure, Bato, Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0001488

₱187,830.00 · FY2024

Released to Marinduque State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱23,822,954.12

Progress

Reported complete (DPWH)

Start Date

March 18, 2024

Target End

January 11, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.