Flood Control and Drainage19DC0025

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS MANAGEMENT PROGRAM, CONS

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS MANAGEMENT PROGRAM, CONS is a DPWH-tracked public work in Batangas 3rd DEO, Region IV-A. Reported contract value: ₱53,074,354.92. Status: Reported complete (DPWH). Contractor on record: V R PATRON BUILDERS. Figures trace to dpwh.

Batangas 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-19-0014483

₱60,000.00 · FY2019

Released to Bata National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

312 projects · ₱14.3B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MISSING LINKS / NEW ROADSGENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD (EAST - WEST ROAD), NASUGBU SECTION, PACKAGE 3, BATANGAS

Region IV-A, Region IV-A

2025₱327.6M
Ongoing (DPWH-reported)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-NAGA-JCT. MAGARAO-CANAMAN-LIBMANAN JCT. PPH ROAD (SKYBRIDGE), CAMARINES SUR PACKAGE 2, MAGARAO, CAMARINES SUR (

Region V, Region V

2024₱273.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT POBLACION BARANGAY I, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱244.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF MISSING LINKS / NEW ROADSGENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD (EAST - WEST ROAD), INDANG - EAST SECTION, PACKAGE 4, CAVITE

Region IV-A, Region IV-A

2023₱209.4M
Past target date (DPWH On-Going)
No sat.

FY 2018 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF MISSING LINKS/NEW ROADS GEN. AGUINALDO-MAGALLANES-NASUGBU ROAD (EAST-WEST RD. AMADEO SECT., CAVITE

Region IV-A, Region IV-A

2018₱193.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARE

Batangas 3rd DEO, Region IV-A

2018₱193.0M
Reported complete (DPWH)
View all 312 projects →

4. Implementation

Contract Amount

₱53,074,354.92

Progress

Reported complete (DPWH)

Start Date

July 26, 2019

Target End

July 19, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.