Roads17FG0050

CONSTRUCTION OF ZONE 4 AND 5, BRGY. STA. ELENA FMR, BRGY. STA. ELENA, IRIGA CITY - STA.0+000-STA. 0+502.50IRIGA CITY

CONSTRUCTION OF ZONE 4 AND 5, BRGY. STA. ELENA FMR, BRGY. STA. ELENA, IRIGA CITY - STA.0+000-STA. 0+502.50IRIGA CITY is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱4,765,481.95. Status: Reported complete (DPWH). Contractor on record: NVF CONST. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱1,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures (Patitinan ES and HS Slope Protection), Brgy. Patitinan, Sagnay, Camarines Sur
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0009159

₱86,116.00 · FY2017

Released to Division of Camarines Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

13 projects · ₱81.0M total · 0 flags

4. Implementation

Contract Amount

₱4,765,481.95

Progress

Reported complete (DPWH)

Start Date

August 22, 2017

Target End

October 22, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.