Rehabilitation / Major Repair of Flood Control Structure22CK0057

Rehabilitation of Existing Dike along Lucung River, Sta. 4+859 to Sta. 4+314, D/S of Santiago Bridge (Jefmin Section, Left Bank), Concepcion, Tarlac

Rehabilitation of Existing Dike along Lucung River, Sta. 4+859 to Sta. 4+314, D/S of Santiago Bridge (Jefmin Section, Left Bank), Concepcion, Tarlac is a DPWH-tracked public work in CONCEPCION (TARLAC), TARLAC, Region III. Reported contract value: ₱57,899,409.79. Status: Reported complete (DPWH). Contractor on record: R R RICAFORT CONST AND SUPPLIES. Figures trace to sumbong.

CONCEPCION (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱46,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure Along Tarlac River Control Left Dike, Sembrano - Sta. Lucia Section (Phase IV), Gerona, Tarlac
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-22-0013107

₱2,999,000,000.00 · FY2022

Released to Tarlac 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0005156

₱20,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004759

₱542,182.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002922

₱811,709,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004769

₱50,540.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0005139

₱71,901.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002779

₱320,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱57,899,409.79

Progress

Reported complete (DPWH)

Start Date

February 16, 2022

Target End

October 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.