Flood Control and Drainage23PL0014

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF GATUMAY DAN FLOOD CONTROL AT BARANGAY CABARUAN, TABUK CITY, KALINGA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF GATUMAY DAN FLOOD CONTROL AT BARANGAY CABARUAN, TABUK CITY, KALINGA is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱19,053,115.91. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: YUNAKIM CONST. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Gatumay Dan Flood Control at Barangay Cabaruan, Tabuk City, Kalinga
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-23-0025489

₱187,786,705.00 · FY2023

Released to Pangasinan State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

58 projects · ₱1.1B total · 0 flags

Other projects by this contractor

No sat.

COMPLETION OF FOUR-STOREY LIBRARY BUILDING, BULANAO CAMPUS - PHASE 2 - KALINGA STATE UNIVERSITY, BULANAO, TABUK CITY, KALINGA

Cordillera Administrative Region, Cordillera Administrative Region

2024₱124.3M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD CONTROL MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE (RIGHT BANK SALTAN SECTION), PINUKPUK, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2023₱96.2M
Reported complete (100% progress, DPWH status On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF TAGGAY-MABIGA (PINUKPUK)-BASSAO-TAWANG (BALBALAN) ROAD, PINUKPUK

Lower Kalinga DEO, Cordillera Administrative Region

2023₱77.1M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - MT. PROVINCE BOUNDARY-CALANAN-PINUKPUK-ABBUT ROAD

Upper Kalinga DEO, Cordillera Administrative Region

2018₱51.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - MANUEL S. AGYAO BOULEVARD - K0510 + 084 - K0510 + 387, K0514 + 549 - K0514 + 789, K0518 + 000 - K0519 + 317, K0525 + 59

Lower Kalinga DEO, Cordillera Administrative Region

2025₱50.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF UPPER CHICO RIVER IRRIGA

Lower Kalinga DEO, Cordillera Administrative Region

2024₱42.8M
Past target date (DPWH On-Going)
View all 58 projects →

4. Implementation

Contract Amount

₱19,053,115.91

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 20, 2023

Target End

July 8, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.