GAA 2024 SUCs Infrastructure Projects24P00083

COMPLETION OF FOUR-STOREY LIBRARY BUILDING, BULANAO CAMPUS - PHASE 2 - KALINGA STATE UNIVERSITY, BULANAO, TABUK CITY, KALINGA

COMPLETION OF FOUR-STOREY LIBRARY BUILDING, BULANAO CAMPUS - PHASE 2 - KALINGA STATE UNIVERSITY, BULANAO, TABUK CITY, KALINGA is a DPWH-tracked public work in Cordillera Administrative Region, Cordillera Administrative Region. Reported contract value: ₱124,343,868.66. Status: Past target date (DPWH On-Going). Contractor on record: YUNAKIM CONST. Figures trace to dpwh.

Cordillera Administrative Region, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

58 projects · ₱1.1B total · 0 flags

Other projects by this contractor

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD CONTROL MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE (RIGHT BANK SALTAN SECTION), PINUKPUK, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2023₱96.2M
Reported complete (100% progress, DPWH status On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF TAGGAY-MABIGA (PINUKPUK)-BASSAO-TAWANG (BALBALAN) ROAD, PINUKPUK

Lower Kalinga DEO, Cordillera Administrative Region

2023₱77.1M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - MT. PROVINCE BOUNDARY-CALANAN-PINUKPUK-ABBUT ROAD

Upper Kalinga DEO, Cordillera Administrative Region

2018₱51.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - MANUEL S. AGYAO BOULEVARD - K0510 + 084 - K0510 + 387, K0514 + 549 - K0514 + 789, K0518 + 000 - K0519 + 317, K0525 + 59

Lower Kalinga DEO, Cordillera Administrative Region

2025₱50.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF UPPER CHICO RIVER IRRIGA

Lower Kalinga DEO, Cordillera Administrative Region

2024₱42.8M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE - CONSTRUCTION OF NEW BRIDGES - GAPPU BR. ALONG TABUK-BANAWE VIA TANUDAN-BARLIG RD

Lower Kalinga DEO, Cordillera Administrative Region

2024₱35.3M
Past target date (DPWH On-Going)
View all 58 projects →

4. Implementation

Contract Amount

₱124,343,868.66

Progress

Past target date (DPWH On-Going)

Start Date

February 10, 2025

Target End

December 22, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.