Buildings and Facilities23EA0087

CONSTRUCTION OF 1STY 2CL SCHOOL BUILDING FOR AURORA SEVILLA SOTTO ELEMENTARY SCHOOL, GASAN, MARINDUQUE

CONSTRUCTION OF 1STY 2CL SCHOOL BUILDING FOR AURORA SEVILLA SOTTO ELEMENTARY SCHOOL, GASAN, MARINDUQUE is a DPWH-tracked public work in Marinduque DEO, Region IV-B. Reported contract value: ₱5,349,268.84. Status: Reported complete (DPWH). Contractor on record: G T J CONST. Figures trace to dpwh.

Marinduque DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱6,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Banuyo, Gasan, Marinduque
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-23-0024672

₱2,500,000.00 · FY2023

Released to 0000000 National Library of - the Philippines (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

104 projects · ₱1.3B total · 0 flags

4. Implementation

Contract Amount

₱5,349,268.84

Progress

Reported complete (DPWH)

Start Date

December 18, 2023

Target End

March 14, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.