Roads16E00074

CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO SABSABAN FALLS & ECO PARK, STA. 000+000.00 - STA. 007+460.00 (UPPER), STA. 007+000.00 - STA. 007+260.00 (LOWER), ARIBUNGOS, BROOKE'S POINT, PALAWAN

CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO SABSABAN FALLS & ECO PARK, STA. 000+000.00 - STA. 007+460.00 (UPPER), STA. 007+000.00 - STA. 007+260.00 (LOWER), ARIBUNGOS, BROOKE'S POINT, PALAWAN is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱134,941,141.63. Status: Reported complete (DPWH). Contractor on record: IVY MICHELLE CONST AND TRADING INC FORMERLY:IVY MICHELLE TRADING. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

150 projects · ₱12.2B total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD, BATARAZA-RIZAL CROSS COUNTRY (SUMBILING-CANIPAAN), PACKAGE B, PALAWA

Region IV-B, Region IV-B

2023₱282.6M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD, PACKAGE B, STA. 3+391.16-STA. 6+097.16, BATAR

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD PACKAGE C, STA. 6+097.16-STA. 9+297.66, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD PACKAGE A, STA. 0+000.00-STA. 3+391.16, BATA

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF PANAS-TAGBITA DIVERSION ROAD PACKAGE B, STA. 0+000.00-STA. 2+585.00, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF PANAS-TAGBITA DIVERSION ROAD, PACKAGE A, STA. 0+000-STA. 2+820, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2025₱279.3M
Past target date (DPWH On-Going)
View all 150 projects →

4. Implementation

Contract Amount

₱134,941,141.63

Progress

Reported complete (DPWH)

Start Date

July 21, 2016

Target End

July 19, 2017

5. Audit