Water Provision and Storage20LC0098

CONSTRUCTION OF WATER SYSTEM-LEVEL II/III, BRGY. STA. CRUZ, PANABO CITY

CONSTRUCTION OF WATER SYSTEM-LEVEL II/III, BRGY. STA. CRUZ, PANABO CITY is a DPWH-tracked public work in Davao del Norte DEO, Region XI. Reported contract value: ₱1,940,398.17. Status: Reported complete (DPWH). Contractor on record: MICAH CONST. Figures trace to dpwh.

Davao del Norte DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Lasang River Flood Control (Upstream of Lasang Bridge), Panabo, Davao del Norte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROI-20-0006704

₱1,437,596.00 · FY2020

Released to Davao del Norte DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,940,398.17

Progress

Reported complete (DPWH)

Start Date

February 24, 2020

Target End

August 1, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.