Construction of Flood Mitigation Structure23CB0026

Construction of Flood Control Structure along Abo-abo River (Downstream) City of Balanga, Bataan

Construction of Flood Control Structure along Abo-abo River (Downstream) City of Balanga, Bataan is a DPWH-tracked public work in CITY OF BALANGA (CAPITAL) (BATAAN), BATAAN, Region III. Reported contract value: ₱57,900,000.00. Status: Reported complete (DPWH). Contractor on record: DAJ BUILDERS / POLYMER-VIC CONST. Figures trace to sumbong.

CITY OF BALANGA (CAPITAL) (BATAAN), BATAAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Capitangan River (Phase II-AA), Abucay, Bataan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-23-002534

₱12,248,151.00 · FY2023

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱57.9M total · 0 flags

4. Implementation

Contract Amount

₱57,900,000.00

Progress

Reported complete (DPWH)

Start Date

February 20, 2023

Target End

December 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.