Buildings and Facilities24JD0032

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY NASIBAC, LEON B. POSTIGO, ZAMBOANGA DEL NORTE

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY NASIBAC, LEON B. POSTIGO, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Zamboanga del Norte 3rd DEO, Region IX. Reported contract value: ₱4,455,000.00. Status: Reported complete (DPWH). Contractor on record: MJMARI BUILDERS AND DEVELOPMENT CORP FORMERLY: MJMARI BUILDERS AND ENT. Figures trace to dpwh.

Zamboanga del Norte 3rd DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Talinga River ( Upstream ) , Talinga, Leon B. Postigo, Zamboanga del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-24-0016030

₱6,897,380.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱4,455,000.00

Progress

Reported complete (DPWH)

Start Date

February 7, 2024

Target End

June 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.