GAA 2024 OO-124BA0008

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/NEW ROADS -SAN VICENTE-SAVIDUG-CHAVAYAN-SUMNANGA-NAKANMUAN ROAD, CHAVAYAN, SABTANG, PACKAGE 1, BATANES

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/NEW ROADS -SAN VICENTE-SAVIDUG-CHAVAYAN-SUMNANGA-NAKANMUAN ROAD, CHAVAYAN, SABTANG, PACKAGE 1, BATANES is a DPWH-tracked public work in Batanes DEO, Region II. Reported contract value: ₱48,978,476.73. Status: Past target date (DPWH On-Going). Contractor on record: MJMARI BUILDERS AND DEVELOPMENT CORP FORMERLY: MJMARI BUILDERS AND ENT. Figures trace to dpwh.

Batanes DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱14,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Phase I, Barangay Sumnanga, Sabtang, Batanes
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Batanes DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

168 projects · ₱2.2B total · 2 flags

4. Implementation

Contract Amount

₱48,978,476.73

Progress

Past target date (DPWH On-Going)

Start Date

April 1, 2024

Target End

July 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.