Construction of Drainage Structure22OA0061

Construction of Box-Culvert Drainage along Sanciangco St. (Gov. Pascual Ave. to Bustamante St.), Malabon City

Construction of Box-Culvert Drainage along Sanciangco St. (Gov. Pascual Ave. to Bustamante St.), Malabon City is a DPWH-tracked public work in CITY OF MALABON (METROPOLITAN MANILA), MALABON CITY, National Capital Region. Reported contract value: ₱9,800,000.00. Status: Reported complete (DPWH). Contractor on record: SKYSCRAPERPH CONST CORP. Figures trace to sumbong.

CITY OF MALABON (METROPOLITAN MANILA), MALABON CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Floodgates along Navotas Coastal Dike, Navotas City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-22-0016012

₱1,665,124,014.00 · FY2022

Released to Malabon-Navotas District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002943

₱100,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003178

₱633,500,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001963

₱35,500,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002648

₱40,615,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002645

₱224,500,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,800,000.00

Progress

Reported complete (DPWH)

Start Date

February 15, 2022

Target End

October 12, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.