Flood Control and Drainage17I00019

CONSTRUCTION/EXTENSION OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURES, JULITA, LEYTE, 2ND LD

CONSTRUCTION/EXTENSION OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURES, JULITA, LEYTE, 2ND LD is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱57,894,574.98. Status: Reported complete (DPWH). Contractor on record: EZJONES CONST INC. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

287 projects · ₱36.2B total · 7 flags

Other projects by this contractor

View all 287 projects →

4. Implementation

Contract Amount

₱57,894,574.98

Progress

Reported complete (DPWH)

Start Date

March 23, 2017

Target End

October 8, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.