Buildings and Facilities17CN0078

REHABILITATION OF COVERED COURT, SAN LUIS CENTRAL SCHOOL, AURORA LONE DISTRICT

REHABILITATION OF COVERED COURT, SAN LUIS CENTRAL SCHOOL, AURORA LONE DISTRICT is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱2,782,666.67. Status: Reported complete (DPWH). Contractor on record: MORNING STEEL CONST. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control Project (Riprap Revetment), Brgy. Pingit, Baler, Aurora Lone District
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-16-0026246

₱890,370.00 · FY2016

Released to Camarines Sur Polytechnic Colleges (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,782,666.67

Progress

Reported complete (DPWH)

Start Date

May 3, 2017

Target End

August 30, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.