Flood Control and Drainage16CI0013

FMS;CONST/MAINT OF FMSDS;SLPOE PROTECTION WORKS ALONG QUITANGIL CREEK, MABALACAT,PAMP

FMS;CONST/MAINT OF FMSDS;SLPOE PROTECTION WORKS ALONG QUITANGIL CREEK, MABALACAT,PAMP is a DPWH-tracked public work in Pampanga 3rd DEO, Region III. Reported contract value: ₱46,057,460.71. Status: Reported complete (DPWH). Contractor on record: NORTHERN BUILDERS. Figures trace to dpwh.

Pampanga 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Balibago Creek, Pampanga 1st LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-16-0019498

₱262,169.00 · FY2016

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱46,057,460.71

Progress

Reported complete (DPWH)

Start Date

March 15, 2016

Target End

October 10, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.