Buildings and Facilities24DP0025

CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BALIMBING, NAGCARLAN, LAGUNA

CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BALIMBING, NAGCARLAN, LAGUNA is a DPWH-tracked public work in Laguna 3rd DEO, Region IV-A. Reported contract value: ₱4,796,550.00. Status: Reported complete (DPWH). Contractor on record: L P O ENT. Figures trace to dpwh.

Laguna 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure for Masapang Br. 1 ( B02881LZ ) , Victoria, Laguna
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-D-24-0003323

₱41,453,000.00 · FY2024

Released to Laguna 3rd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

160 projects · ₱2.0B total · 0 flags

4. Implementation

Contract Amount

₱4,796,550.00

Progress

Reported complete (DPWH)

Start Date

April 11, 2024

Target End

September 7, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.