Roads24OD0233

INSTALLATION/ APPLICATION OF SIGNAGE AND PAVEMENT MARKINGS, AND ZEBRA PEDESTRIAN CROSSING ALONG A. MABINI ST. - K0008 + 855 - K0009 + 917, BARANGAY 13, CALOOCAN CITY

INSTALLATION/ APPLICATION OF SIGNAGE AND PAVEMENT MARKINGS, AND ZEBRA PEDESTRIAN CROSSING ALONG A. MABINI ST. - K0008 + 855 - K0009 + 917, BARANGAY 13, CALOOCAN CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱3,572,507.73. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: TWO DIMENSION CONST. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along Sampaguita Creek, Barangay 171, Caloocan City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-24-0005592

₱0.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

98 projects · ₱2.0B total · 0 flags

Other projects by this contractor

View all 98 projects →

4. Implementation

Contract Amount

₱3,572,507.73

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 26, 2024

Target End

July 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.