Roads21J00101

CONSTRUCTION OF SULIGPANG TO GARID ROAD, LUUK, SULU

CONSTRUCTION OF SULIGPANG TO GARID ROAD, LUUK, SULU is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱24,642,998.92. Status: Reported complete (DPWH). Contractor on record: ZHEREB CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱24,642,998.92

Progress

Reported complete (DPWH)

Start Date

May 25, 2021

Target End

September 24, 2021

5. Audit