Buildings and Facilities15BD0121

CONSTRUCTION OF MULTI-PURPOSE BUILDING (MPB), BARANGAY BUGNAY, TUAO, CAGAYAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING (MPB), BARANGAY BUGNAY, TUAO, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱1,940,978.65. Status: Reported complete (DPWH). Contractor on record: DEKM CONST 32409. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,940,978.65

Progress

Reported complete (DPWH)

Start Date

March 24, 2016

Target End

July 6, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.