GAA 2025 OO-125K00180

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, ILIGAN CITY COASTAL BYPASS ROAD, PACKAGE 21, ILIGAN CITY

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, ILIGAN CITY COASTAL BYPASS ROAD, PACKAGE 21, ILIGAN CITY is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱70,051,051.15. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: TRIPARCO DEVELOPMENT CORP. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

357 projects · ₱29.2B total · 4 flags

Other projects by this contractor

View all 357 projects →

4. Implementation

Contract Amount

₱70,051,051.15

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 26, 2025

Target End

December 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.