Buildings and Facilities23CJ0201

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL HALL BUILDING) SANTA IGNACIA, TARLAC (PHASE 1)

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL HALL BUILDING) SANTA IGNACIA, TARLAC (PHASE 1) is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱29,379,158.89. Status: Reported complete (DPWH). Contractor on record: AD PINEDA CONST. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Cubcub, Mayantoc, Tarlac
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-23-002689

₱687,586,680.00 · FY2023

Released to 1300085 Home Office - (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱29,379,158.89

Progress

Reported complete (DPWH)

Start Date

May 15, 2023

Target End

December 10, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.