Roads15FL0074

CONST. OF BARANGAY ROAD (CLUSTER X) LAJONG-NABURAKAN, BRGY. NABURAKAN, MATNOG, SOR. AND BRGY. CABAGA

CONST. OF BARANGAY ROAD (CLUSTER X) LAJONG-NABURAKAN, BRGY. NABURAKAN, MATNOG, SOR. AND BRGY. CABAGA is a DPWH-tracked public work in Sorsogon 2nd DEO, Region V. Reported contract value: ₱3,738,277.03. Status: Reported complete (DPWH). Contractor on record: STEVEN CONST. Figures trace to dpwh.

Sorsogon 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cogon Gully, Downstream Section, Brgy. Cogon, Irosin, Sorsogon
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-16-0024682

₱613,199.00 · FY2016

Released to 000 - Governance Commission for Government-Owned To cover Per (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

252 projects · ₱7.4B total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION AND IMPROVEMENT OF FLOOD CONTROL STRUCTURES ALONG TAGAYTAY RIVER, BRGY. TAGAYTAY-BARIW, CAMALIG, ALBAY, CAMALIG, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱164.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 - PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF LEFT AND RIGHT SIDE UGSONG RIVER FLOOD CONTROL STRUCT

Albay 3rd DEO, Region V

2025₱138.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION_IMPROVEMENT OF ACCESS ROADS LEADING TO TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-MATNOG-BULAN-MAGALLANES WEST COAST HIGHWAY, SORSOGON PACKAGE I MAGALLANES, SORSOGON

Sorsogon DEO, Region V

2022₱108.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION_IMPROVEMENT OF ACCESS ROADS LEADING TO TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-MATNOG-BULAN-MAGALLANES WEST COAST HIGHWAY, SORSOGON PACKAGE II, MAGALLANES, SORSOGON

Sorsogon DEO, Region V

2022₱106.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-MATNOG-BULAN-MAGALLANES WEST COAST HIGHWAY, SORSOGON PACKAGE I MAGALLANES, SORSOGON

Sorsogon DEO, Region V

2021₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION_IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM-KATUPARAN)-ACCESS ROAD LEADING TO SORSOGON CITY PORT, SORSOGON

Sorsogon DEO, Region V

2023₱93.6M
Reported complete (DPWH)
View all 252 projects →

4. Implementation

Contract Amount

₱3,738,277.03

Progress

Reported complete (DPWH)

Start Date

February 4, 2016

Target End

March 24, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.