Roads25AB0102

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONCRETING OF M. VICENTE - LAMPITOC ROAD, BRGY. TABTABAGAN AND BRGY. BUGASI, BANNA, ILOCOS NORTE

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONCRETING OF M. VICENTE - LAMPITOC ROAD, BRGY. TABTABAGAN AND BRGY. BUGASI, BANNA, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱18,640,049.64. Status: Past target date (DPWH On-Going). Contractor on record: BJMJB CONST. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱27,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation/Drainage Structure from Barangay San Francisco, Brgy. San Baltazar, Brgy. San Ildefonso, Brgy. San Bartolome, Brgy. San Silvestre and San Juan Bautista, San Nicolas, Ilocos Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVII-25-0008435

₱2,533,000.00 · FY2025

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

360 projects · ₱4.5B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATING STRUCTURE RIGHT BANK, BARANGAY ISIC-ISIC, VINTAR ILOCOS NORTE (PHASE 2)

Ilocos Norte 1st DEO, Region I

2024₱57.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATIONSTRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OFFLOOD CONTROL STRUCTURE ALONG PADSAN RIVER, BARANGAY10, SARRAT, ILOCOS NORTE (PHASE 2)

Ilocos Norte 1st DEO, Region I

2024₱57.9M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, SITIO DALIM, BARANGAY CABAYO, VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱56.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, SANJERA BENGBENGKAG, BARANGAY ISIC-ISIC, VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱56.1M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DAURAO CREEK, BARANGAY CAAOACAN, LAOAG CITY, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱55.6M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE MANGATO BRIDGE UPSTREAM, LAOAG CITY, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱55.6M
Past target date (DPWH On-Going)
View all 360 projects →

4. Implementation

Contract Amount

₱18,640,049.64

Progress

Past target date (DPWH On-Going)

Start Date

May 27, 2025

Target End

January 18, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.