Construction of Revetment22KB0032

Construction of Revetment, Downstream and Upstream of Camp I Bridge along Maramag River, Barangay Camp I, Maramag, Bukidnon

Construction of Revetment, Downstream and Upstream of Camp I Bridge along Maramag River, Barangay Camp I, Maramag, Bukidnon is a DPWH-tracked public work in MARAMAG (BUKIDNON), BUKIDNON, Region X. Reported contract value: ₱39,200,000.00. Status: Reported complete (DPWH). Contractor on record: PYRAMID CONSOLIDATED BUILDERS & GEN MDSE. Figures trace to sumbong.

MARAMAG (BUKIDNON), BUKIDNON, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along CDO City Dominorog Camp Kibaritan Rd (Upstream and Downstream of Tal-uban Bridge) Phase 3, Talakag, Bukidnon
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0010240

₱100,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005381

₱5,751,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003123

₱718,520,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005382

₱572,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003061

₱3,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-22-0002605

₱1,087,000.00 · FY2022

Released to Bureau of Animal Industry (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱39,200,000.00

Progress

Reported complete (DPWH)

Start Date

February 7, 2022

Target End

February 1, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.