Bridges18KC0099

RECONSTRUCTION OF MAKABUNDOL HANGING BRIDGE, DANATAG, BAUNGON, BUKIDNON

RECONSTRUCTION OF MAKABUNDOL HANGING BRIDGE, DANATAG, BAUNGON, BUKIDNON is a DPWH-tracked public work in Bukidnon 3rd DEO, Region X. Reported contract value: ₱6,566,825.00. Status: Reported complete (DPWH). Contractor on record: LBL TRAFFIC CONTROL AND CONST SERVICES. Figures trace to dpwh.

Bukidnon 3rd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of slope protection along Jct SH Manolo Fortich-Libona-Indahag Road (upstream & downstream) of Agusan Canyon Bridge, Bukidnon
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVIII-18-0005873

₱1,778,742.00 · FY2018

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱6,566,825.00

Progress

Reported complete (DPWH)

Start Date

July 2, 2018

Target End

November 13, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.