Construction of Flood Mitigation Structure24EB0046

Construction of Flood Mitigation Structure, Barangay 7, Mamburao, Occidental Mindoro

Construction of Flood Mitigation Structure, Barangay 7, Mamburao, Occidental Mindoro is a DPWH-tracked public work in MAMBURAO (CAPITAL) (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B. Reported contract value: ₱9,848,740.48. Status: Reported complete (DPWH). Contractor on record: STX ENT. Figures trace to sumbong.

MAMBURAO (CAPITAL) (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay 5, Mamburao, Occidental Mindoro
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-24-0010131

₱42,148,921.00 · FY2024

Released to Mindoro Occidental District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008377

₱1,894,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0018309

₱207,904.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008389

₱175,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0003735

₱112,448.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,848,740.48

Progress

Reported complete (DPWH)

Start Date

February 8, 2024

Target End

May 5, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.