Rehabilitation / Major Repair of Flood Control Structure23CK0064

Rehabilitation of Existing Dike along Rio Chico River (Macalong Section, Right Bank), Package 1, La Paz, Tarlac, Sta. 2+755 to Sta.3+231

Rehabilitation of Existing Dike along Rio Chico River (Macalong Section, Right Bank), Package 1, La Paz, Tarlac, Sta. 2+755 to Sta.3+231 is a DPWH-tracked public work in LA PAZ (TARLAC), TARLAC, Region III. Reported contract value: ₱96,494,805.62. Status: Reported complete (DPWH). Contractor on record: JAM-C BUILDERS / AMP 723 CONST CORP FORMERLY: A M P CONST. Figures trace to sumbong.

LA PAZ (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Cubcub, Mayantoc, Tarlac
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVII-23-0026612

₱1,825,596.00 · FY2023

Released to 0000000 Cebu Normal - University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱96.5M total · 0 flags

4. Implementation

Contract Amount

₱96,494,805.62

Progress

Reported complete (DPWH)

Start Date

March 17, 2023

Target End

December 7, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.