Flood Control and Drainage24GD0042

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, PANITAN RIVER CONTROL (UPSTREAM), PANITAN, CAPIZ

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, PANITAN RIVER CONTROL (UPSTREAM), PANITAN, CAPIZ is a DPWH-tracked public work in Capiz 1st DEO, Region VI. Reported contract value: ₱55,002,130.36. Status: Past target date (DPWH On-Going). Contractor on record: JASA GD 2000 CONST CORP FORMERLY:JASA BUILDER'S 31330. Figures trace to dpwh.

Capiz 1st DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Barangay VI and VII, Roxas City, Capiz
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Capiz 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 31330

240 projects · ₱9.7B total · 0 flags

Other projects by this contractor

View all 240 projects →

4. Implementation

Contract Amount

₱55,002,130.36

Progress

Past target date (DPWH On-Going)

Start Date

June 24, 2024

Target End

March 30, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.