Roads25A00177

CONSTRUCTION OF MISSING LINKS/ NEW ROADS - BOLINAO - DASOL COASTAL ROAD, PANGASINAN

CONSTRUCTION OF MISSING LINKS/ NEW ROADS - BOLINAO - DASOL COASTAL ROAD, PANGASINAN is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱187,247,070.25. Status: Past target date (DPWH On-Going). Contractor on record: JASA GD 2000 CONST CORP FORMERLY:JASA BUILDER'S. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

243 projects · ₱9.9B total · 0 flags

Other projects by this contractor

No sat.

AVIATION INFRASTRUCTURE PROGRAM, LOCALLY-FUNDED PROJECTS, CONSTRUCTION/REHABILITATION AND IMPROVEMENT OF OTHER TRANSPORTATION INFRASTRUCTURE-AVIATION, SIQUIJOR AIRPORT, SIQUIJOR

Region VII, Region VII

2021₱435.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRA/FACILITIES-CONST. OF SEAWALL PROTECTION STRUCTURES (PHASE I), ORION, BATAAN, PROVINCE OF BATAAN

Region III, Region III

2024₱241.2M
Past target date (DPWH On-Going)

CONSTRUCTION OF REVETMENT WALL ALONG POLO RIVER, VALENZUELA CITY

Metro Manila 3rd DEO, National Capital Region

2018₱210.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ACCESS ROAD LEADING TO MAPITA TRIBAL COMMUNITY AND VIEW DECK TO NAYONG AGUILAR (YLANG-YLANG PLANTATION AND AGRI-TOURISM DESTINATION), PHASE II, BRGY. LAOAG, AGUILAR, PANGA

Region I, Region I

2018₱164.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ACCESS ROAD LEADING TO MAPITA TRIBAL COMMUNITY AND VIEW DECK TO NAYONG AGUILAR (YLANG-YLANG PLANTATION AND AGRI-TOURISM DESTINATION), PHASE I, BRGY. LAOAG, AGUILAR, PANGAS

Region I, Region I

2018₱163.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATATIONS,POBLACION-SAN JOSE-NAMAGBAGAN-IMBO-TONDOL ROAD,LEADING TO TONDOL BEACH,ANDA, PANGASINAN, INCLUDING CONSTRUCTION OF STA RITA BRIDGE, NAMAGBAGAN BRIDGE AND TONDOL BRIDGE

Region I, Region I

2016₱159.1M
Reported complete (DPWH)
View all 243 projects →

4. Implementation

Contract Amount

₱187,247,070.25

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2025

Target End

January 26, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.