Buildings and Facilities22JF0044

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BUYOGAN, SIAY, ZAMBOANGA SIBUGAY

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BUYOGAN, SIAY, ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱1,960,368.65. Status: Reported complete (DPWH). Contractor on record: BARILLO CONST AND ENT. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tupilac River (Phase III) R.T. Lim, Zamboanga Sibugay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-22-0007894

₱5,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

140 projects · ₱2.5B total · 0 flags

Other projects by this contractor

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION/IMPROVEMENT OF FLOOD CONTROL FOR PREVENTION AND MITIGATION ALONG BRGY. SAN JOSE-POBLACION IMELDA, PART OF SIBUGUEY RIVER, IMELDA, Z

Region IX, Region IX

2019₱112.1M
Reported complete (DPWH)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG KABASALAN RIVER (PHASE III), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY

Region IX, Region IX

2021₱105.1M
Reported complete (DPWH)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE IV), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY

Region IX, Region IX

2022₱104.9M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), DOWNSTREAM, CANACAN, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 1

Region IX, Region IX

2023₱104.8M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), DOWNSTREAM, CANACAN, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 2

Region IX, Region IX

2023₱100.0M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 1

Region IX, Region IX

2023₱100.0M
Reported complete (100% progress, DPWH status On-Going)
View all 140 projects →

4. Implementation

Contract Amount

₱1,960,368.65

Progress

Reported complete (DPWH)

Start Date

March 2, 2022

Target End

May 10, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.