Roads22CI0076

CONVERGENCE AND SPECIAL SUPPORT PROGRAM; SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES: REHAB OF ROAD PHASE 3 AT ANGELES CITY, PAMPANGA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM; SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES: REHAB OF ROAD PHASE 3 AT ANGELES CITY, PAMPANGA is a DPWH-tracked public work in Pampanga 3rd DEO, Region III. Reported contract value: ₱79,118,555.22. Status: Reported complete (DPWH). Contractor on record: B-12 CONST AND TRADING CORP. Figures trace to dpwh.

Pampanga 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure/Slope Protection of Mesalipit Creek, Bacolor, Pampanga
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-22-0008163

₱38,865,479.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

164 projects · ₱8.7B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-JOSE ABAD SANTOS AVENUE (JASA), PROVINCE OF PAMPANGA

Region III, Region III

2023₱156.3M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS, JOSE ABAD SANTOS AVENUE (JASA), PROVINCE OF PAMPANGA

Region III, Region III

2020₱151.1M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS / FACILITIES - REHABILITATION OF STA. ANA - MAGALANG ROAD (SAN PABLO - ARENAS PORTION) PHASE I,

Pampanga 1st DEO, Region III

2025₱137.5M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF DEL ROSARIO - CALULUT ROAD, CITY OF SAN FERNANDO, PAMPANGA

Pampanga 1st DEO, Region III

2025₱137.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-ROAD WIDENING-PRIMARY ROADS, JOSE ABAD SANTOS AVENUE (JASA), PAMPANGA 2ND LEGISLATIVE DISTRICT, PROVINCE OF PAMPANGA

Region III, Region III

2018₱132.6M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MALINO - SUCLABAN BYPASS ROAD, CITY OF SAN FERNANDO, PAMPANGA

Pampanga 1st DEO, Region III

2025₱130.7M
Past target date (DPWH On-Going)
View all 164 projects →

4. Implementation

Contract Amount

₱79,118,555.22

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

June 21, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.