Construction of Flood Mitigation Structure24EI0072

Construction of Banus River Control, Barangay Malayong-Barangay Manguyang Section, Gloria, Oriental Mindoro

Construction of Banus River Control, Barangay Malayong-Barangay Manguyang Section, Gloria, Oriental Mindoro is a DPWH-tracked public work in GLORIA (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B. Reported contract value: ₱48,997,248.42. Status: Reported complete (DPWH). Contractor on record: LUMEL GLENN CONST. Figures trace to sumbong.

GLORIA (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Canturing River Flood Control, Brgy. Nasaug, Segment 2, Maasin City, Southern Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-24-0004447

₱9,492,576.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0006527

₱5,615,052.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008383

₱1,386,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004004

₱564,186.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0002609

₱25,000,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004024

₱237,954.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004305

₱193,512.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008398

₱128,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0006528

₱521,819.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0020130

₱20,000,000.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱48,997,248.42

Progress

Reported complete (DPWH)

Start Date

March 4, 2024

Target End

December 4, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.