Flood Control and Drainage23DH0040

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ROMELO IN BARANGAYS HALAYHAYIN AND MENDIOLA, SINILOAN, LAGUNA

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ROMELO IN BARANGAYS HALAYHAYIN AND MENDIOLA, SINILOAN, LAGUNA is a DPWH-tracked public work in Laguna 1st DEO, Region IV-A. Reported contract value: ₱57,600,008.14. Status: Reported complete (DPWH). Contractor on record: WAWAO BUILDERS. Figures trace to dpwh.

Laguna 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Malaban, Bi±an City, Laguna
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-23-0018875

₱2,159,414.00 · FY2023

Released to 0000000 Guimaras State - College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

F

164 projects · ₱9.2B total · 15 flags

4. Implementation

Contract Amount

₱57,600,008.14

Progress

Reported complete (DPWH)

Start Date

March 22, 2023

Target End

December 31, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.