Buildings and Facilities25AA0581

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 29 STO. TOMAS, LAOAG CITY, ILOCOS NORTE

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 29 STO. TOMAS, LAOAG CITY, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱4,850,786.66. Status: Past target date (DPWH On-Going). Contractor on record: ZEDIK CONST AND DEV'T CORP. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Mangato, Laoag City, Ilocos Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-25-0008479

₱38,977,790.00 · FY2025

Released to Ilocos Norte 1st DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

F

33 projects · ₱215.0M total · 0 flags

Other projects by this contractor

View all 33 projects →

4. Implementation

Contract Amount

₱4,850,786.66

Progress

Past target date (DPWH On-Going)

Start Date

February 17, 2025

Target End

May 17, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.